All edge closets have been successfully converted to the new Cisco gear.

Academic & Administrative Buildings

Building Conversion Date Notes
Kunkel Hall October 19 Completed
Van Wickle Hall October 19 Completed
Hugel Science Center October 22 Completed
Markle Hall October 23 Completed
Oechsle Hall October 24 Completed
Purchasing October 25 Completed
Parsons Street October 25 Completed
Pfenning Alumni Center October 25 Completed
Williams Center for the Arts October 25 Completed
Kirby Sports Center October 26 Completed
Pardee Hall November 2 Completed
Hogg Hall November 2 Completed
Portlock Black Cultural Center November 2 Completed
Simon Center November 2 Completed
Bailey Health Center November 3 Completed
Farinon College Center November 3 Completed
Plant Operations November 6 Completed
President's House November 6 Completed
Maroon Club Strength Center November 6 Completed
Print Studios November 8 Completed
Kirby Hall of Civil Rights November 8 Completed
Plant Ops Supply Bldg November 9 Completed
Ramer History House November 9 Completed
Williams Visual Arts Bldg November 9 Completed
Bourger Varsity Football House November 9 Completed
Fisher Press Box November 9 Completed
AEC November 12-14 Completed

Residence Halls

Building Conversion Date Notes
Skillman Library August 14 Completed
Keefe Hall September 27 Completed
Watson Hall October 1 Completed
Kirby House October 2 Completed
Ramer Hall October 3 Completed
Farber Hall October 3 Completed
South College October 4 Completed
KDR October 4 Completed
Phi Gamma Delta October 4 Completed
Sigma Nu October 5 Completed
McKeen Hall October 5 Completed
Gates Hall October 5 Completed
Soles Hall October 5 Completed
Watson Courts October 5 Completed
Zeta Psi October 5 Completed
Fisher Hall East October 8 Completed
Pi Beta Phi October 8 Completed
PT Farinon House October 8 Completed
2 West (Tri Delta) October 8 Completed
Lerch House (KKG) October 8 Completed
DKE October 8 Completed
Phi Kappa Psi October 8 Completed
Fisher Hall West October 9 Completed
Rubin Hall October 9 Completed
Kamine Hall October 9 Completed
Easton Hall October 9 Completed
Ruef Hall October 9 Completed
Alpha Phi October 10 Completed
Conway House October 10 Completed
Four West October 10 Completed
Marquis Hall October 11 Completed
Reeder House October 11 Completed
McKelvy House October 11 Completed
Hamilton House October 25 Completed

Return to Network Upgrade Project Home

12/17/07